This blog is made with the aim of sharing experiences in life and working in various fields of science and knowledge of engineering (mechanical, electrical, instrumentation, civil), quality, safety, environmental, legal, economic, social and cultural, as well as other fields. It is expected that stated in this blog can be useful for visitors.
Tuesday, 8 August 2017
Conan Elliot - Batam | Tokopedia
Conan Elliot - Batam | Tokopedia: Belanja online aman dan nyaman dari Conan Elliot - Terjangkau & Berkualitas
Monday, 13 June 2016
How to improve the Pump Reliability
Many pump reliability problems are closely related to over-sizing pumps, which leads to highly restricted discharge valve operation, and flow-rates are far below the best efficiency point (BEP), which are associated with low hydraulic efficiencies and high discharge pressures.
You can take the 10 steps below to achieve sustainable pump reliability are:
1. Proper Design and Equipment Selection
A complete and accurate specification is the first step to establishing a reliable pumping system. Pump specifications should spell out all operating requirements and operating parameters, including:
Many design engineers tend to specify oversized pumps and excessive horsepower drivers on the premise that it is better to err on the side of having too much power for the application than too little. And if the flow of the system is too high coming out of the pump, it simply can be throttled in the discharge side. This approach, although very common, is a very inefficient and very costly way to design a system. It increases energy costs for operating the pumping system, reduces the operating life of the equipment and will most likely increase the frequency of failure.
To understand why this is true, you have to understand the basics of how a pump works. Centrifugal pumps operate with a rotating impeller that imparts velocity energy to a liquid. The impeller accelerates the liquid and discharges it into the casing and, as the casing area increases, the velocity energy is converted to pressure. Higher velocity brings higher pressure.
Pumps are designed for specific flow ranges. When a pump is sized properly and is operating optimally, or at its BEP, liquid flow is constant and radial forces acting on the impeller are at a minimum. This allows the pump to experience the highest efficiencies and lowest vibration. If the pump runs off-BEP at an increased or reduced flow rate, an imbalance of pressure will occur inside the pump. This imbalance can cause shaft deflection, excessive loads on bearings and mechanical seals, excessive vibration and heat, all of which significantly reduce the life of the pump and increase the likelihood of premature failure. Because the majority of pump operating conditions are dynamic and actual flow and pressure requirements fluctuate, it makes it extremely important to size the pump to operate at or near its BEP.
Pumps operating away from BEP display a myriad of issues, none of which contribute to good reliability or efficiency. BEP occurs when the angle of the fluid entering the eye of the impeller is parallel to the impeller blade. Operating away from BEP changes the angle of the fluid to the inlet vane and increases the possibility of premature or catastrophic failure of the pump. By causing suction or discharge recirculation, or cavitations, this leads to excessive vibration, increased shaft deflection, increased bearing loads and reduced seal life.
2. Proper Installation and Commissioning
When a pump is delivered to a site, it's important to take time to inspect it to ensure it matches the order information and has not been damaged. If the pump is stored for less than six months, you only need to store it in a clean, dry environment that is free from contamination and excessive heat and vibration to keep it in good condition. If the pump is stored for more than six months, continue to follow these same guidelines and also begin to rotate the shaft by hand at least every three months to prevent brinelling of the bearing surfaces.
It is important to provide a rigid and flat concrete foundation that weighs two to three times as much as the pump. This will absorb any type of vibration and should prevent strain and distortion when you tighten the foundation bolts. There is much detail to preparing a proper foundation and the vendor's installation manual is a good reference for keeping things on track.
Another good practice is to never draw piping into place by using force at the flanged connections of the pump. This can introduce significant strains on the unit and cause misalignment between the pump and driver. Pipe strain adversely affects the operation of the pump, which may result in physical injury and/or damage to the equipment.
Installation and commissioning represent a very small portion of the overall total cost of ownership. However, improper installation and commissioning will result in problems that significantly reduce the reliability of the pump. These problems often do not surface for a period of time and can require significant time and cost to resolve (example: redesign, base plate or foundation replacement, piping modifications, etc.). Often these issues are not resolved due to the time and cost required to solve them, thus resulting in reduced life and higher cost of ownership.
Here are some wise rules to follow during installation to avoid premature failure:
3. Proper Flow Control
Flow control is a very important element for optimizing the efficiency and lifecycle cost of a pumping system. Controlling flow by throttling a valve in the discharge line is a widely used approach for controlling the flow, but is generally very inefficient and costly in the long run. Pumping fluid against a partially closed control valve consumes tremendous amounts of energy and can cause premature pump failure. This method of flow control modifies the point in which the system curve intersects the pump curve and, if it is significantly away from BEP, pump life will be diminished.
During the design phase, variable frequency drive (VFD) should be evaluated for flow control. VFD cost more to purchase and install and aren't feasible for every situation, but in many cases, smaller horsepower requirements and increased energy efficiency can offset the initial cost. The utilization of a VFD allows the pump to remain close to BEP over a range of flow by varying the speed of the driver. The VFD allows the pump curve to be adjusted along the system curve as opposed to the use of a control valve that modifies the system curve.
Another method of flow control is the use of a bypass line with a fixed speed driver. This method allows the flow through the pump to remain constant, hopefully at BEP, while modulating the flow rates downstream and diverting some of the fluid back to the source. Under no circumstances should the pump flow be adjusted from the suction side of the pump. In doing so, the risk of pump damage far exceeds any possible benefit. Modifying the flow from the suction side of the pump will result in reduced pump life and unsafe conditions that could destroy the equipment and cause serious injury or death.
4. Proper Operation
During operation of the pump, critical performance elements like flow, pressure, temperature, vibration, current load and cleanliness should be continuously monitored to ensure the pumping system is operating efficiently and effectively. It is crucial that pumps are sized properly and operate at the optimum speed to meet the flow and head requirements while remaining at the BEP for the majority of run time. And it is extremely important to operate the pump properly to guarantee that the equipment will reach its useful design life and for the safety of plant personnel. Pump damage (bearing/seal) is cumulative. Regardless of the level of damage, it remains with the components until the parts are ultimately replaced. Multiple episodes of improper operation will cause the pump to fail prematurely.
Some pump operation rules to follow are:
Failure to follow these rules may result in elevated temperatures, excessive vibration, potential flashing of liquid, cavitations and excessive pressure build-up, which may lead to catastrophic or premature equipment failure, personnel injury, or death.
5. Proper Maintenance
Maintenance is extremely important to establish and follow a rigorous maintenance program to keep pumps in good operating condition and maximize their useful life.
Maintaining pumps is fairly straightforward; you generally do the same things you do to any rotating equipment. In our experience, the highest cause of pump failure is improper operation that causes seal failure and improper lubrication that causes premature bearing failure.
The first order of business is to establish a condition-monitoring program that includes as many technologies that can be justified. Conditions that should be considered that require some investment in technology are:
Acceptable ranges should be established for each of these parameters with actual readings compared each time they are taken. Readings should be trended over time to identify any trends that require further analysis. Many computerized maintenance management systems are capable of having these conditions directly entered into the system electronically and will provide trend charts for timely analysis.
Other conditions that should be considered by more traditional time-based preventive maintenance activities are:
Professional planning and scheduling techniques must be employed to ensure all condition-monitoring and preventive maintenance activities are properly planned and scheduled. To ensure the right actions are performed at the right frequency and action is taken to resolve any issues resulting from the routines, planning and scheduling cannot be emphasized enough. After all, the issues that are resolved before they evolve into breakdowns are the returns from the condition-monitoring/preventive maintenance investment.
6. Stock the Right Parts
One of the easiest and fastest ways to improve pump reliability is to use parts that meet the manufacturer’s original specifications. In the pump industry, there are many parts replicators that sell replacement parts at reduced prices. Unfortunately, many times these parts do not meet specifications and do not have adequate quality procedures in place. Invariably, when we are asked to perform root-cause analysis for our customers, these substandard parts are the culprit. If you choose to buy parts from replicators, make sure the supplier demonstrates the specifications and quality procedures that are used to produce the parts. But remember, the only time it makes sense to buy parts from replicators is when the original specified parts are no longer available.
To minimize the amount of parts stored in the store-room, you should consider a power end exchange and repair contract with your supplier that will provide you with replacement power ends that are remanufactured to the original specifications and, in most cases, come with an as-new warranty. This approach minimizes the parts that are stocked in the store-room and reduces failures caused by improper rebuild procedures. Mean time to repair can be reduced by replacing power ends, as opposed to a complete replacement or rebuild when a failure occurs. This approach can also minimize the duration of production interruptions.
If you choose to stock the parts necessary to perform your own in-house repairs, make sure you refer to the manufacturer’s recommended repair parts list and stock the minimum amount required for each class of pump in your operation. Parts should be stored in a clean, dry environment and clearly marked with the appropriate stock or bin number for easy retrieval. Set appropriate min/max levels in your stores system to support the operation and set up an automatic replenishment process. If you store complete units or power ends, American Petroleum Institute recommends that you rotate the shaft 1¼ turns on a monthly basis to prevent bearing flat spots and work hardened areas on the shaft.
7. Monitor Efficiency
Monitoring pump efficiency can be a very worthwhile endeavor in most manufacturing plants. Engineers and designers generally err on the side of over-sizing pumping systems and do not always provide control systems that optimize energy consumption. Another factor is, as plants grow and are modified over time, pumping systems are not modified to perform the new requirements efficiently.
Two major factors that determine pump system efficiency are where the pump is running on the pump curve relative to BEP and what type of control system is used to control the pump output. Pumping against a partially closed valve is a terribly inefficient way to control pump output.
With these factors in mind, pumping system efficiency should be continuously monitored to ensure process demands are met at the lowest possible cost.
8. Track Lifecycle History
Data from computerized maintenance management systems (CMMS), when properly recorded and analyzed, will provide the data necessary to continuously improve performance and reduce the cost of your pumping systems. From the analysis of this data, you can determine root-causes, identify “bad actor” equipment and eliminate repetitive failures that, when resolved, offer tremendous potential for improving the company’s bottom line.
If you use your CMMS religiously to plan and schedule all activities, record accurate data from the work performed and analyze data on a routine basis, then you are well on your way to tracking the lifecycle history of your equipment. The only thing remaining is taking action on the findings from the analysis you performed.
9. Establish a Pump Management Program
Many of customers have created teams consisting of management, technical, operations and maintenance resources that meet regularly and use these principles to improve existing pumping systems. These teams make sure the proper systems are purchased for new designs and expansions. When you consider the statistics outlined in the opening paragraph of this article, the opportunity to reduce spending and improve performance becomes apparent.
10. Establish a Configuration Management Process
To maintain the integrity and accuracy of the data and information in your systems, there must be a process in place designed to continuously monitor the changes you make to your equipment and processes, plus update the information on a timely basis. Configuration management is that process and can be likened to a management of change process where equipment data, specifications, drawings, spare parts and other technical data is updated any time you make changes in the manufacturing process, modifications or upgrades to existing equipment, install new equipment, or discard obsolete equipment.
You can take the 10 steps below to achieve sustainable pump reliability are:
1. Proper Design and Equipment Selection
A complete and accurate specification is the first step to establishing a reliable pumping system. Pump specifications should spell out all operating requirements and operating parameters, including:
- BEP of the selected pump
- Net Positive Suction Head Available (NPSHA)
- Flow rate
- Pressure
- Speed
- Voltage
- Fluid type
- Specific gravity and PH
- Metallurgy
- Inlet and outlet pipe sizes
- Operating temperature
- Viscosity
- Solids Present
- Chemical reactivity
- Vapor pressure
- Entrained air/gases
- Seal arrangement
- Bearing lubrication method
- Pipe size and configuration
- Physical location and environment
To understand why this is true, you have to understand the basics of how a pump works. Centrifugal pumps operate with a rotating impeller that imparts velocity energy to a liquid. The impeller accelerates the liquid and discharges it into the casing and, as the casing area increases, the velocity energy is converted to pressure. Higher velocity brings higher pressure.
Pumps are designed for specific flow ranges. When a pump is sized properly and is operating optimally, or at its BEP, liquid flow is constant and radial forces acting on the impeller are at a minimum. This allows the pump to experience the highest efficiencies and lowest vibration. If the pump runs off-BEP at an increased or reduced flow rate, an imbalance of pressure will occur inside the pump. This imbalance can cause shaft deflection, excessive loads on bearings and mechanical seals, excessive vibration and heat, all of which significantly reduce the life of the pump and increase the likelihood of premature failure. Because the majority of pump operating conditions are dynamic and actual flow and pressure requirements fluctuate, it makes it extremely important to size the pump to operate at or near its BEP.
Pumps operating away from BEP display a myriad of issues, none of which contribute to good reliability or efficiency. BEP occurs when the angle of the fluid entering the eye of the impeller is parallel to the impeller blade. Operating away from BEP changes the angle of the fluid to the inlet vane and increases the possibility of premature or catastrophic failure of the pump. By causing suction or discharge recirculation, or cavitations, this leads to excessive vibration, increased shaft deflection, increased bearing loads and reduced seal life.
2. Proper Installation and Commissioning
When a pump is delivered to a site, it's important to take time to inspect it to ensure it matches the order information and has not been damaged. If the pump is stored for less than six months, you only need to store it in a clean, dry environment that is free from contamination and excessive heat and vibration to keep it in good condition. If the pump is stored for more than six months, continue to follow these same guidelines and also begin to rotate the shaft by hand at least every three months to prevent brinelling of the bearing surfaces.
It is important to provide a rigid and flat concrete foundation that weighs two to three times as much as the pump. This will absorb any type of vibration and should prevent strain and distortion when you tighten the foundation bolts. There is much detail to preparing a proper foundation and the vendor's installation manual is a good reference for keeping things on track.
Another good practice is to never draw piping into place by using force at the flanged connections of the pump. This can introduce significant strains on the unit and cause misalignment between the pump and driver. Pipe strain adversely affects the operation of the pump, which may result in physical injury and/or damage to the equipment.
Installation and commissioning represent a very small portion of the overall total cost of ownership. However, improper installation and commissioning will result in problems that significantly reduce the reliability of the pump. These problems often do not surface for a period of time and can require significant time and cost to resolve (example: redesign, base plate or foundation replacement, piping modifications, etc.). Often these issues are not resolved due to the time and cost required to solve them, thus resulting in reduced life and higher cost of ownership.
Here are some wise rules to follow during installation to avoid premature failure:
- Locate the pump as close to the liquid source as possible.
- Make sure there is adequate space around and above the pump for safety, ventilation, inspection, installation/removal and maintenance.
- Protect the unit from weather and water damage due to rain, flooding and freezing temperatures.
- Do not install and operate the equipment in closed systems unless the system is constructed with properly-sized safety devices and control devices.
- Take into consideration the occurrence of unwanted noise and vibration.
- Follow all safety, installation, alignment, startup, shutdown and operating procedures outlined in the vendor's manual.
- Utilize API standards or ASME standards, where applicable.
- Ensure that the distance between the inlet flange of the pump and the closest elbow is at least five pipe diameters. This minimizes the risk of cavitation in the suction inlet of the pump due to turbulence.
- Ensure that elbows in general do not have sharp bends and that the suction piping is one or two sizes larger than the suction inlet of the pump.
- The suction piping must never have a smaller diameter than the suction inlet of the pump.
- Ensure that no part of the suction piping extends below the suction flange of the pump, is adequately below the surface of the liquid source and is level or sloping downward from the liquid source.
- Net positive suction head available (NPSHA) must always exceed NPSH required (NPSHR).
- When checking rotation prior to start-up, disconnect the pump from the driver to prevent the pump from operating in reverse rotation. Reverse rotation can result in the direct contact of metal parts, excessive heat generation and catastrophic failure.
Flow control is a very important element for optimizing the efficiency and lifecycle cost of a pumping system. Controlling flow by throttling a valve in the discharge line is a widely used approach for controlling the flow, but is generally very inefficient and costly in the long run. Pumping fluid against a partially closed control valve consumes tremendous amounts of energy and can cause premature pump failure. This method of flow control modifies the point in which the system curve intersects the pump curve and, if it is significantly away from BEP, pump life will be diminished.
During the design phase, variable frequency drive (VFD) should be evaluated for flow control. VFD cost more to purchase and install and aren't feasible for every situation, but in many cases, smaller horsepower requirements and increased energy efficiency can offset the initial cost. The utilization of a VFD allows the pump to remain close to BEP over a range of flow by varying the speed of the driver. The VFD allows the pump curve to be adjusted along the system curve as opposed to the use of a control valve that modifies the system curve.
Another method of flow control is the use of a bypass line with a fixed speed driver. This method allows the flow through the pump to remain constant, hopefully at BEP, while modulating the flow rates downstream and diverting some of the fluid back to the source. Under no circumstances should the pump flow be adjusted from the suction side of the pump. In doing so, the risk of pump damage far exceeds any possible benefit. Modifying the flow from the suction side of the pump will result in reduced pump life and unsafe conditions that could destroy the equipment and cause serious injury or death.
4. Proper Operation
During operation of the pump, critical performance elements like flow, pressure, temperature, vibration, current load and cleanliness should be continuously monitored to ensure the pumping system is operating efficiently and effectively. It is crucial that pumps are sized properly and operate at the optimum speed to meet the flow and head requirements while remaining at the BEP for the majority of run time. And it is extremely important to operate the pump properly to guarantee that the equipment will reach its useful design life and for the safety of plant personnel. Pump damage (bearing/seal) is cumulative. Regardless of the level of damage, it remains with the components until the parts are ultimately replaced. Multiple episodes of improper operation will cause the pump to fail prematurely.
Some pump operation rules to follow are:
- The suction valve is 100 percent open at all times.
- Discharge flow is adjusted to ensure that there is adequate back pressure to eliminate water hammer or running out to maximum flow.
- Pump is primed and air vented prior to start up.
- Seal flush systems are operational prior to start up.
- Lubrication is at proper level and meets specified quality standards.
- Pump must be operated at a speed to maintain adequate flow through the pumping system.
- Pumps should not be operated for long periods of time at maximum flow rate.
- Do not operate the pump without coupling guards correctly installed.
- Pumps should not be operated with the discharge valve completely closed for extended periods of time.
- Do not allow the pump to rotate in reverse.
5. Proper Maintenance
Maintenance is extremely important to establish and follow a rigorous maintenance program to keep pumps in good operating condition and maximize their useful life.
Maintaining pumps is fairly straightforward; you generally do the same things you do to any rotating equipment. In our experience, the highest cause of pump failure is improper operation that causes seal failure and improper lubrication that causes premature bearing failure.
The first order of business is to establish a condition-monitoring program that includes as many technologies that can be justified. Conditions that should be considered that require some investment in technology are:
- Flow
- Pressure
- Temperature
- Vibration
- Ultrasound
- Power usage
Other conditions that should be considered by more traditional time-based preventive maintenance activities are:
- Lubrication issues
- Seal device issues
- Cleanliness
- Proper air flow
- Foundation or base-plate/base-frame issues
- Piping system hangers and support integrity
- Inspect coupling guards
- Loose bolts
6. Stock the Right Parts
One of the easiest and fastest ways to improve pump reliability is to use parts that meet the manufacturer’s original specifications. In the pump industry, there are many parts replicators that sell replacement parts at reduced prices. Unfortunately, many times these parts do not meet specifications and do not have adequate quality procedures in place. Invariably, when we are asked to perform root-cause analysis for our customers, these substandard parts are the culprit. If you choose to buy parts from replicators, make sure the supplier demonstrates the specifications and quality procedures that are used to produce the parts. But remember, the only time it makes sense to buy parts from replicators is when the original specified parts are no longer available.
To minimize the amount of parts stored in the store-room, you should consider a power end exchange and repair contract with your supplier that will provide you with replacement power ends that are remanufactured to the original specifications and, in most cases, come with an as-new warranty. This approach minimizes the parts that are stocked in the store-room and reduces failures caused by improper rebuild procedures. Mean time to repair can be reduced by replacing power ends, as opposed to a complete replacement or rebuild when a failure occurs. This approach can also minimize the duration of production interruptions.
If you choose to stock the parts necessary to perform your own in-house repairs, make sure you refer to the manufacturer’s recommended repair parts list and stock the minimum amount required for each class of pump in your operation. Parts should be stored in a clean, dry environment and clearly marked with the appropriate stock or bin number for easy retrieval. Set appropriate min/max levels in your stores system to support the operation and set up an automatic replenishment process. If you store complete units or power ends, American Petroleum Institute recommends that you rotate the shaft 1¼ turns on a monthly basis to prevent bearing flat spots and work hardened areas on the shaft.
7. Monitor Efficiency
Monitoring pump efficiency can be a very worthwhile endeavor in most manufacturing plants. Engineers and designers generally err on the side of over-sizing pumping systems and do not always provide control systems that optimize energy consumption. Another factor is, as plants grow and are modified over time, pumping systems are not modified to perform the new requirements efficiently.
Two major factors that determine pump system efficiency are where the pump is running on the pump curve relative to BEP and what type of control system is used to control the pump output. Pumping against a partially closed valve is a terribly inefficient way to control pump output.
With these factors in mind, pumping system efficiency should be continuously monitored to ensure process demands are met at the lowest possible cost.
8. Track Lifecycle History
Data from computerized maintenance management systems (CMMS), when properly recorded and analyzed, will provide the data necessary to continuously improve performance and reduce the cost of your pumping systems. From the analysis of this data, you can determine root-causes, identify “bad actor” equipment and eliminate repetitive failures that, when resolved, offer tremendous potential for improving the company’s bottom line.
If you use your CMMS religiously to plan and schedule all activities, record accurate data from the work performed and analyze data on a routine basis, then you are well on your way to tracking the lifecycle history of your equipment. The only thing remaining is taking action on the findings from the analysis you performed.
9. Establish a Pump Management Program
Many of customers have created teams consisting of management, technical, operations and maintenance resources that meet regularly and use these principles to improve existing pumping systems. These teams make sure the proper systems are purchased for new designs and expansions. When you consider the statistics outlined in the opening paragraph of this article, the opportunity to reduce spending and improve performance becomes apparent.
10. Establish a Configuration Management Process
To maintain the integrity and accuracy of the data and information in your systems, there must be a process in place designed to continuously monitor the changes you make to your equipment and processes, plus update the information on a timely basis. Configuration management is that process and can be likened to a management of change process where equipment data, specifications, drawings, spare parts and other technical data is updated any time you make changes in the manufacturing process, modifications or upgrades to existing equipment, install new equipment, or discard obsolete equipment.
The configuration management process should be triggered by engineering and supported by management when changes are made to the design or operation of the plant. Included in the process is the provision that all affected plant personnel are given access to new information and training is provided to ensure safe and efficient operations and maintenance of the new equipment or processes.
If you have embraced all steps above in your pump management program, you have optimized the cost and efficiency of your pumping systems and know and understand the value for doing this. This may seem like a lot of effort to keep pumping systems running reliably, but when you compare it to the cost of continuous inefficiency and repeat failures, it makes it all worthwhile. Remember, everything you learn about keeping pumping systems running effectively and efficiently can be directly applied to all other assets, making this investment even more valuable.
If you have embraced all steps above in your pump management program, you have optimized the cost and efficiency of your pumping systems and know and understand the value for doing this. This may seem like a lot of effort to keep pumping systems running reliably, but when you compare it to the cost of continuous inefficiency and repeat failures, it makes it all worthwhile. Remember, everything you learn about keeping pumping systems running effectively and efficiently can be directly applied to all other assets, making this investment even more valuable.
Sunday, 12 June 2016
KESABARAN
Sekalipun ada keuntungan untuk
menjadi yang pertama, tetapi
terdapat lebih banyak keuntungan dalam menjadi yang terbaik.
Di dunia yang serba instan dan segera ini, layaklah kita melihat
bagaimana melakukan sesuatu secara sepantasnya.
Di dunia yang serba instan dan segera ini, layaklah kita melihat
bagaimana melakukan sesuatu secara sepantasnya.
Terburu-buru dan ketidak sabaran
adalah bisa berakibat fatal
dan rentan terhadap kesalahan. Pelajarilah nilai kesabaran.
Sekalipun rasanya seperti anda tertinggal jauh di belakang,
tetapi dengan usaha yang terukur dan tekun, lebih mungkin
anda akan berada di depan.
Kesabaran bukan berarti menunda-nunda pekerjaan. Kesabaran
berarti mengambil tindakan SEKARANG, yang akan membawa hasil
di masa depan. Kesabaran berfokus pada hasil terbaik – bukan
pada hasil tercepat atau termudah. Kesabaran berarti mengerti
bahwa perjalanan panjang memiliki hasil yang panjang pula.
dan rentan terhadap kesalahan. Pelajarilah nilai kesabaran.
Sekalipun rasanya seperti anda tertinggal jauh di belakang,
tetapi dengan usaha yang terukur dan tekun, lebih mungkin
anda akan berada di depan.
Kesabaran bukan berarti menunda-nunda pekerjaan. Kesabaran
berarti mengambil tindakan SEKARANG, yang akan membawa hasil
di masa depan. Kesabaran berfokus pada hasil terbaik – bukan
pada hasil tercepat atau termudah. Kesabaran berarti mengerti
bahwa perjalanan panjang memiliki hasil yang panjang pula.
Mulailah dari sekarang, dan
bersabarlah. Siapa yang mencari
hasil segera – akan segera pula kehilangan hasilnya – itupun
kalau mereka bisa mendapatkan hasil.
Memang makan waktu untuk menghasilkan yang
terbaik, tetapihasil segera – akan segera pula kehilangan hasilnya – itupun
kalau mereka bisa mendapatkan hasil.
anda sendiri yang akan menikmati hasilnya…
Pump Hydraulic Efficiency
Pump Hydraulic Efficiency is defined as below:

Use formula below to calculate the pump system efficiency:
Pump System Efficiency = Pump Hydraulic Power Output / Motor Shaft Power
Pump Hydraulic Power Output = (Flow Capacity x Head x Density x gravity) / 3.6 x 10⁶
Motor Shaft Power = Electrical Power Consumed x Motor Efficiency
Where:
Flow Capacity : In m³/h (Measured by flow meter Flexim F601)
Head : In m (Checked to the pressure gauge)
Density : In kg/m³ (Measured or checked to the Fluid Density Table)
gravity : 9.81 m/s²
Electrical Power Consumed : In kW (Measured by Power Logger Fluke 1735)
Motor Efficiency : In % (Checked to the nameplate or motor datasheet)

Use formula below to calculate the pump system efficiency:
Pump System Efficiency = Pump Hydraulic Power Output / Motor Shaft Power
Pump Hydraulic Power Output = (Flow Capacity x Head x Density x gravity) / 3.6 x 10⁶
Motor Shaft Power = Electrical Power Consumed x Motor Efficiency
Where:
Flow Capacity : In m³/h (Measured by flow meter Flexim F601)
Head : In m (Checked to the pressure gauge)
Density : In kg/m³ (Measured or checked to the Fluid Density Table)
gravity : 9.81 m/s²
Electrical Power Consumed : In kW (Measured by Power Logger Fluke 1735)
Motor Efficiency : In % (Checked to the nameplate or motor datasheet)